For the purposes of this section,“bitumen mine development project”, of a taxpayer, means a project the taxpayer undertakes for the sole purpose of developing a new mine to extract and process tar sands from a mineral resource of the taxpayer to produce bitumen or a similar product;
“completion”, of a specified oil sands mine development project, means the first attainment of a level of average output, attributable to the project and measured over a 60-day period, equal to at least 60% of the planned level of average daily output (as determined in paragraph b of the definition of “specified oil sands mine development project”);
“designated asset”, in respect of an oil sands mine development project of a taxpayer, means a property that is a building, a structure, machinery or equipment and is, or is an integral and substantial part of,(a) in the case of a bitumen mine development project,i. a crusher,
ii. a froth treatment plant,
iii. a primary separation unit,
iv. a steam generation plant,
v. a cogeneration plant, or
vi. a water treatment plant; or
(b) in the case of a bitumen upgrading development project,i. a gasifier unit,
ii. a vacuum distillation unit,
iii. a hydrocracker unit,
iv. a hydrotreater unit,
v. a hydroprocessor unit, or
vi. a coker;
“oil sands mine development project”, of a taxpayer, means a bitumen mine development project or a bitumen upgrading development project;
“preliminary work activity”, in respect of a taxpayer’s oil sands mine development project, means any activity that is preliminary to the acquisition, construction, fabrication or installation by or on behalf of the taxpayer of designated assets in respect of the project including, in particular, the following activities:(a) obtaining permits or regulatory approvals;
(b) performing design or engineering work;
(c) conducting feasibility studies;
(d) conducting environmental assessments; and
(e) entering into contracts;
“specified oil sands mine development project”, of a taxpayer, means an oil sands mine development project (not including any preliminary work activity) in respect of which(a) one or more designated assets was, before 22 March 2011, acquired by the taxpayer or in the process of being constructed, fabricated or installed, by or on behalf of the taxpayer; and
(b) the planned level of average daily output (where that output is bitumen or a similar product in the case of a bitumen mine development project, or synthetic crude oil or a similar product in the case of a bitumen upgrading development project) that can reasonably be expected, is the lesser ofi. the level that was the demonstrated intention of the taxpayer on 21 March 2011 to produce from the oil sands mine development project, and
ii. the maximum level of output associated with the design capacity, on 21 March 2011, of the designated assets referred to in paragraph a.